Gantt
Chart Weekly Timescale View |
The Gantt chart view displays task information about your project
as bar graph. On the right side of this view, the project is displayed
using a bar chart. The bar chart will show duration, start date
and finish date. The relative position of the Gantt bars shows the
sequence in which your project tasks are scheduled to occur.
A PERT chart is
a diagram that shows dependencies between project tasks. This
is also known as a Network Diagram. Boxes or nodes represent project
tasks and lines that connect the boxes represent task dependencies.
The boxes contain data about the task. The top portion of the
box is the status bar, the task name is next. The remainder of
the box is made up of the four rectangles with the left top rectangle
containing the task ID. The bottom left rectangle contains the
start date of the task. The right top rectangle contains the duration.
The right bottom rectangle contains the finish date.
|
|